The countdown is on! Acqua Beachside Residences, Palm Beach, is on track for construction completion in approximately November 2019.
The structure is nearing completion with the structural steel for the roof due to commence soon.
The internal finishes within the building are well advanced with partition sheeting up to level five.
Painting is well underway, and the joinery and tiling installation is complete all the way to level three.
Stone tops are being installed as well as the timber flooring, giving the apartments are modern coastal vibe.
Externally, balustrade framing installation has commenced and external building render is largely complete behind the scaffolding on levels one through to four.
All trunk services – water, sewer, stormwater drainage, electricity supply and NBN are connected to the building and the gas connection is due to take place in the next two weeks; which finalises all trunk service connections required for the project.