SIARN - CRU CONSTRUCT UPDATE - JUNE

With the basement one slab poured late May, the focus for June was all about getting the ground floor slab prepared and poured. 

C2647.00 00 23 10.Still001

The basement one walls were sprayed and vertical concrete walls complete. Columns and lift core where constructed, including blockwork stairwell walls. 

The large tubular braces supporting the perimeter wall were removed allowing the formwork to ground floor slab to be installed, reinforcement and services installed to achieve the ground floor concrete to be poured late June. 

IMG 2244

The dewatering system was then decommissioned and removed from site.  The commencement of scaffolding installation kicks off in July while works commence internally in basement two with the installation of power and lighting.

C2647.00 00 33 02.Still002

 

Information relating to construction updates is a general summary only and may be subject to change depending on construction programs, suppliers, external contractors or weather events.