In spite of heavy rainfall through February and early March, good progress has been made on the highly anticipated townhomes under construction at award-winning Currumbin estate, Arcadia Rise.
Internal progress
With our tiling completed and joinery with stone tops installed in our most advanced units, we commenced the installation of robe doors and stair balustrades in preparation for final fit off works. This is consistent across units 13 to 23, Externally, the retaining walls commenced to allow preparation for the upcoming external concreting and landscaping works.
As the tiling works in Units 1 to 12 progressed, joinery installation followed closely behind along with the installation of the internal stairs and early painting works.
External progress
The focus this month has been completing roofing and with the face brickwork completed, external cladding and rendering works are also underway.
Sales enquiries
With prices starting at $559,900 for a three-bedroom, double garage home perfectly designed to showcase smart terrace living without compromise.
Buyers are urged to act now to secure one of the final homes in this much sought after estate. Call 1800 843 278 or email info@arcadiarise.com
Information relating to construction updates is a general summary only and may be subject to change depending on construction programs, suppliers, external contractors or weather events.