The bulk excavation works are completed with the cleaning up of the shoring piles currently being completed for the installation of the membrane and shotcrete, which will be installed after the completion of the basements.
The works to be completed during the following few weeks include completion of inground services and pits, and the concrete blinding layer to site. The builder will also commence forming up of basement 1 slab.