The weather delivered some unwelcome challenges over the last few months, however the builder successfully navigated outcomes to ensure the preliminary works proceeded. The soggy start for the year has seen approximately 1590mm of rainfall in the area, which is almost double the average of 848mm. Despite the inclement weather the builder has completed and installed 250 piles, to approximately 8 metres, totally 400m3 of concrete. Earth works are now underway to remove the guide walls and pile trimming and installation of conduits will commence mid-June for the sinking of power lines.